Excelsior Energy has another bad day…
May 29th, 2009
Yes, Tom Micheletti and Excelsior Energy’s Mesaba Project had another rough time at the Public Utilities Commission yesterday. The PUC was deciding on Excelsior’s Motions for Reconsideration in “Phase II” of the proceedings:
Excelsior’s Motion to Suspend, for Reconsideration etc etc etc
It was fast, the tone seemed to say that the PUC had had enough of it, and wanted to be done. Deny, deny, deny, the end.
So, now what? I don’t know, because Charlotte Neigh, of Citizens Against the Mesaba Project, had inquired with Richard Hargis, of the DOE, as to the status of the EIS in the siting docket, scheduled to be released in June (yeah, right, as if…). He said:
Ms. Neigh,
I don’t think this affects the issuance of the FEIS.
Richard Hargis
Huh… so now what? Haven’t a clue. My client, mncalgasplant.com, was an intervenor in this case, beginning nearly five years ago. Will this thing end some time in my lifetime? I’m starting to wonder…
Leave a Reply