The Bonneville Report on Xmsn and MORE!
January 8th, 2022
I’m cleaning the office, trying to move into 2021 with less reliance on paper and more on electronics. That could be asking for trouble, but the piles and piles I’ve got here, decades of utility work, it’s going to topple the house. So I’m continuing my practice of scanning or finding on-line many of these reports and posting them here so I can find them, and others can too.
Years ago, circa 1999, maybe 2000, during the Arrowhead transmission contested case in either Minnesota, working out of a garage and staying in a tent, or Wisconsin, a two month long hearing from hell, rooming with Cassidy, one of two German Shepherds where we were staying…
… I received a “brown paper envelope” copy of “The Bonneville Report,” a report that was issued by Bonneville Power Administration and very shortly thereafter, it was disappeared, and it later returned. The copy I received was a later version, circa 1996. I present to you World Organization of Landowner Freedom’s Exhibit A:
And here’s a 1989 version:
And here’s another great one that shouldn’t be forgotten, particularly as Xcel’s Benson, in rate case testimony about transmission, notes rehab of the King-Eau Claire-Arpin transmission line:
Northern MAPP/Northwestern Ontario Disturbance June 25, 1998
And…
And an interesting report, wherein Xcel forecasts peak demand:
And as they start the shift to “economic” need:
And for those ready to shut down Prairie Island Nuclear Generation Plant:
And anyone remember when “Wind on the Wires” was a program of the Izaak Walton League? This was in 2001, the beginning of the machinations and set up for the big transmission build-out, the SW Minn 345kV line was the first out the gate, and gave Xcel/NSP the start it needed. And below, read the minutes, this transmission that we’re all paying big bucks for is the impact of the enviro sell-out.
Note the part about the “settlement agreement,” for that SW Minn 345kV line!
And here, introducing “Wind on the Wires,” an Izaaak Walton grant program, “identifying the highest priority transmission upgrades and working with utilities, state and federal regulators, and local communities for their completion.” Thanks a lot:
And a LOT of old Arrowhead info, contracts, costs, even application!
And from the “Wisconsin Western Interface Alternatives” (still looking for online), this precursor of CapX 2020 and MISO’s MVP Portfolio below – which ones HAVEN’T they built?
Saving and posting for posterity…
Transmission in NYT today
February 7th, 2009
Matthew Wald has a good piece in the NYT today, good in that it raises some of the issues, but these issues raised need some more digging, can you dig it?
Check this paragraph from the article:
In fact, energy experts say that simply building a better grid is not enough, because that would make the cheap electricity that comes from burning coal available in more parts of the country. That could squeeze out generators that are more expensive but cleaner, like those running on natural gas. The solution is to put a price on emissions from dirtier fuels and incorporate that into the price of electricity, or find some other way to limit power generation from coal, these experts say.
Not “could,” but WOULD “squeeze out generators that are more expensive but cleaner” and adding externalities to coal generation cost would only stop that, would only be a “solution” if it tacked on HUGE costs, far greater than those anticipated by those advocating either Cap & Trade or Tax.
But those of us in transmission are glad to see the driver for new construction exposed, as it was in the MISO Benefits Study by our good friends at ICF:
RTO operational benefits are largely associated with the improved ability to displace generation with coal generation, more efficient use of coal generation, and better use of import potential.
Here’s that MISO study, the above quote comes from the conclusions, p. 83, and is also stated in the intro — THIS IS THE REASON FOR TRANSMISSION, THIS IS THE REASON FOR THE MIDWEST MISO MARKET. Read the study:
ICF’s Independent Assessment of Midwest ISO Operational Benefits
For example, Jose Delgado whining about hwo long it took to get the permit for Arrowhead, what does he expect for a project that was an absurdly obvious ploy for a superhighway for bulk power portrayed as a “local load” need for WUMS? They put together many options in the WRAO report, and selected one, Arrowhead, “3j,” as the be-all and end-all of transmission. That was declared the ONE line that would fix Wisconsin. Then, next thing you know, they still want to do “5” more commonly known as the Chisago project, they want to do “9” in SW Minnesota claiming “it’s for wind” when there’s only 213-302MVA coming off of Buffalo Ridge into the Nobles substation, they do them all because that’s what they want, they can ship bulk power. It’s been so dishonest… Utilities have been so dishonest…
And let’s look at the financing of these lines. CapX 2020 testimony and a powerpoint demonstrate that they don’t have the financing lined up for that $2 billion dollar project. They were working through Lehman Bros. so what does that say? The “Cap” of CapX 2020 is “Capital” and they don’t have it. But because they want it, they’ll make us pay for it. Is something wrong with this picture?
———————————————–
Hurdles (Not Financial Ones) Await Electric Grid Update
“We burn up three years on a line that will take two months to build,” he said.