Xmsn at House Climate & Energy Committee
February 10th, 2022
Just WOW! Yeah, that WOW too… Today was the meeting of House Climate and Energy Policy and Finance, and check out the presentations:
Attachments:
- HF XXX/BE133 (Stephenson) Permitting Reform – 2/2/2022
- Electric Transmission System Report – 2/3/2022
- Agenda – 2/9/2022
- Minutes for 2-3-22 – 2/9/2022
- Minutes for 2-8-22 – 2/9/2022
- Presentation-Engelking – 2/9/2022
- Presentation-MISO – 2/9/2022
- Presentation-Soholt – 2/9/2022
- Letter-MP – 2/9/2022
- Letter-MRES – 2/9/2022
- Letter-Overland – 2/9/2022
- Presentation-PUC-Updated.pdf – 2/10/2022
The good news is that MRES did have challenges to the proposed language in HF XXX/BE133 (Stephenson) Permitting Reform, but aside from MRES, what a bunch of transmission toadies.
Commerce’s Electric Transmission System Report and a PUC Commissioner ADVOCATING for more transmission Presentation-PUC-Updated.pdf, good grief, there’s just no excuse.
More of this?
No thanks…
Needless to say, I should have pushed to get on the list to testify, a letter isn’t enough.
Minnesota’s nuclear moratorium — gone?!?!?!
May 8th, 2010
I read with horror news of Rep. Bill Hilty’s amendment eliminating the moratorium on new nuclear generating plants that passed in a House Ominous Bill this week. WHAT ARE THESE YAHOOS THINKING? The Senate already approved it, and now the House… and I just can’t see Pawlenty doing anything but signing it with glee.
(sudden feeling of ice picks going through temples… buried in brain… electricity applied…)
AAAAAAAAGH!
Is this the “price” of the rollback of exemptions of utilities from eminent domain laws? Is it an attempt to look like they’re repealing it when “conditions” mean it won’t happen? (like those that said Obama really doesn’t mean what he’s saying about coal gasification or transmission, he knows better) Is it more of the same deal-making that took the Renewable Development Fund away from PrairIe Island Indian Community, or the enviro sell-outs that gave us the 2005 Transmission bill? Minnesota’s second nuclear waste storage facility at Monticello, now two piles piling with no plan in sight, PERMANENT?
What I’m hearing about this from various little birdies….
… is NOT encouraging — ooooohhhhhhh do I have a headache…
… apparently NO ONE OBJECTED!
NO ONE OBJECTED?!?!?!?!
AAAAAAAAGH!
Here’s the bill as it is on the Senate site:
Here’s how Rep. Bill Hilty, Chair of House Energy, amended it:
Page 4, after line 11, insert:
“Sec. 4. [216B.1695] NUCLEAR POWER PLANT; COST RECOVERY.
(a) The commission may not allow any of the following costs attributable to the construction of a nuclear generating plant begun after July 1, 2010, to be recovered from Minnesota ratepayers until the plant begins operating at a monthly load capacity factor of at least 85 percent:
(1) planning, design, safety, environmental, or engineering studies undertaken prior to construction; or
(2) the costs of obtaining regulatory approval, including permits, licenses and any other approval required prior to construction from federal, state and local authorities.
(b) The commission may not allow any of the following costs attributable to the construction of a nuclear generating plant begun after July 1, 2010, to be recovered from Minnesota ratepayers:
Journal of the House – 98th Day – Thursday, May 6, 2010 – Top of Page 11584
(1) any construction costs exceeding the projected construction cost of the generating plant and any ancillary facility constructed by the utility to temporarily or permanently store nuclear waste generated by the plant, as identified in the utility’s certificate of need application submitted under section 216B.243;
(2) the costs of insuring the plant against accidents that exceed the cost of insurance for a fossil fuel plant of equivalent capacity; or
(3) contributions from the plant to provide and maintain local fire protection and emergency services to the plant in case of an accident.
(c) Except for regulatory costs of state agencies, no revenues from taxes or fees imposed by the state of Minnesota may be used to pay for any portion of the preconstruction, construction, maintenance, or operating costs of a nuclear generating plant, or to assume any financial risk associated with an accidental release of radioactivity from the generating plant or an ancillary facility constructed by the utility that owns the generating plant to temporarily or permanently store nuclear waste generated by the plant.
Sec. 5. Minnesota Statutes 2008, section 216B.243, subdivision 3b, is amended to read:
Subd. 3b. Nuclear power plant; new construction prohibited; relicensing. (a) The commission may not issue a certificate of need for the construction of a new nuclear-powered electric generating plant provided that the certificate of need application contains a separate estimate of preconstruction and construction costs that does not include any of the costs identified in section 216B.1695, paragraphs (a) and (b).
(b) Any certificate of need for additional storage of spent nuclear fuel for a facility seeking a license extension shall address the impacts of continued operations over the period for which approval is sought.”
Renumber the sections in sequence and correct the internal references
Amend the title accordingly.
Way below is the list of yeas and nays, do send each of them a missive:
The ones who voted against it are the strangest set of bedfellows! But KUDOS TO THEM!
If you click on this to look at the whole back and forth with amendments, scroll to p. 11579 to start. Here’s the vote:
The bill was read for the third time, as amended, and placed upon its final passage.
Those who voted in the affirmative were:
Those who voted in the negative were: