npslogo

Stop the Lines!!!

National Park Service has extended the deadline for EIS Scoping Comments on the Susquehanna-Roseland transmission project.  WHEW!  Now we have until March 12 to send our comments in!

NPS Home Page for Susquehanna-Roseland Transmission Project

Get your clues on Comments from what they do and do not include:

NPS Internal Scoping Document

It’s in the Pocono Times:

Transmission line public scoping period extended

From the NPS blog:

High public interest has prompted the superintendents of Delaware Water Gap National Recreation Area, the Appalachian National Scenic Trail, and the Middle Delaware National Scenic and Recreational River and National Recreation Water Trail to extend by a week the public comment period on a proposal to run a transmission line across the areas.

The comment period was scheduled to end today, but has been extended through March 12.

“Scoping comments,” those that suggest areas the Park Service should examine in preparing an environmental impact statement, are being taken to help agency managers prepare an EIS on a proposal to replace existing 80-foot transmission towers with larger towers (up to 200 feet high) and add an additional 500 kV transmission line.

Park Service officials say the request would necessitate widening the cleared area and the existing right-of-way and constructing access roads. The proposed expanded line and new towers would impact the Delaware Water Gap National Recreation Area; the Middle Delaware National Scenic and Recreational River and National Recreation Water Trail; and the Appalachian National Scenic Trail.

The EIS will analyze a reasonable range of alternatives to meet project objectives; evaluate potential issues and impacts to the resources and values of the Delaware Water Gap National Recreation Area, Middle Delaware National Scenic and Recreational River, and the Appalachian National Scenic Trail park units, and identify mitigation measures to lessen the degree or extent of these impacts.

There are numerous ways for the public to provide comments on the public scoping phase of the planning process, including leaving a message on the Park Planning Information Telephone Line (570-426-2491), submitting comments online through a link on the National Park Service Planning, Environment and Public Comment site, http://parkplanning.nps.gov (select Appalachian NST or Delaware Water Gap NRA), or by mailing comments to:

National Park Service
Attention: DEWA PPL EIS Planning Team
Denver Service Center-Planning Division
P.O. Box 25287
Denver, CO 80225-0287

Detailed information about the need for the EIS and the project timeline
can be found on the National Park Service Planning, Environment and Public
Comment site:
http://parkplanning.nps.gov.

.

jcsp08-xmsndream

Above, “JCSP,” the Joint Coordinated System Plan.

Repeat after me… EASTERN STATES DON’T WANT OUR MIDWEST TRANSMISSION.

Once more with feeling… EASTERN STATES DON’T WANT OUR MIDWEST TRANSMISSION!!!

And they don’t give a rodent’s rump what we do with our transmission but THEY DO NOT WANT TO PAY FOR IT!

rats-ass

It’s not anything new, but it seems that the message is getting through all the way to Iowa.   Soon Minnesota? The message?  That the east coast does not want Midwest transmission, that they have their own renewables and not only that, they know that transmission from the Midwest means coal and, most importantly, THEY WILL NOT PAY FOR TRANSMISSION FOISTED UPON THEM.

The 7th Circuit case tossing out PJM’s cost apportionment scheme must be having an impact because everyone is freakin’ about cost allocation.  Again, GOOD!  The court said that PJM could not shove the costs of transmission on those who do not benefit from it:

Illinois Commerce Commission v. FERC – August 6, 2009

Enter the Coalition for Fair Transmission Policy, just launched today with a press conference in Washington, D.C.

Dig this from their site:

Assessment of National EHV Transmission Grid Overlay Proposals: Cost-Benefit Methodologies and Claims

HA!  I love it when that happens…

Here’s some background on our Midwest Transmission — transmission we don’t need and they don’t want:

JCSP & UMTDI in the news

This opposition to Midwest transmission is nothing new, I’ve entered documentation in the record in a couple of proceedings now, but what is new is that as of today’s “launch,” there’s now an industry group advocating against Midwest transmission, and that’s one utility interest I’m glad to see hopping mad as hell and not going to take it anymore!  GOOD!  Maybe that will help stop this stupid transmission-fest across the Midwest.

PUC Chair David Boyd had it right when he testified before Minnesota’s Legislative Energy Commission and led off with, “We need a business plan.”  Yes, that’s true, there is no business plan, and there is no MARKET for transmission.  I just hope that message gets through before “we” build and WE have to pay for all these wires in the air!

Here are a few recent posts of mine on this, followed by today’s article in the Des Moines Register.

Offshore transmission, NOT transmission from the Midwest

Eastern Governors stand up against transmission!

And today’s Des Moines Register article:

Eastern states balk at paying wind cost

By DAN PILLER • dpiller@dmreg.com • March 5, 2010


Much of the nation isn’t eager to help pay for a high-voltage transmission line to sell Iowa’s extra wind power to big markets east of the Mississippi River.

“If Iowa wants to build a transmission line for their energy, we have no objection. But Iowa or the Midwest should pay for it,” said Ian Bowles, secretary of energy and environmental affairs in Massachusetts. New England states want to produce their own wind energy from offshore farms.

A coalition of utilities in Eastern states will announce today their opposition to a 765-kilovolt transmission line, more than double the capacity of the current 345-kilovolt lines. The line would send electricity from the Dakotas, Iowa and Minnesota to Chicago and points east. Iowa is the nation’s second-largest producer of wind-generated electricity, behind Texas.

Such a transmission line won public support from President Barack Obama on his visit to Newton last April. It is a linchpin of the renewable energy policies of Gov. Chet Culver and Iowa’s largest electric utility, MidAmerican Energy of Des Moines.

Alliant Energy has its objections

Proposals by MidAmerican and ITC Holdings, which runs transmission lines in eastern Iowa, are considered the best chance for Iowa to reap a wind energy version of the financial windfall enjoyed by Texas and other oil- and gas-producing states.

But as wind energy becomes bigger and more corporate, the utility industry is divided even in Iowa.

Alliant Energy, which serves 525,000 customers in parts of northern, eastern and southern Iowa, has joined the newly organized Coalition for Fair Transmission Policy, which promises to fight a government-mandated transmission line from the Midwest.

“We don’t think the costs of transmission should be socialized,” said Alliant spokesman Ryan Stensland. Alliant’s wind energy production in Iowa is a fraction of MidAmerican’s.

Bruce Edelston, executive director for the Coalition for Fair Transmission Policy, said his group has formed to fight a proposal in the Senate to give the Federal Energy Regulatory Commission authority to site and assess costs for a wind transmission line.

“We don’t think it’s necessarily a good idea to build a multistate transmission line,” said Edelston, whose group will hold a coming-out news conference today in Washington, D.C.

The Fair Transmission group represents companies serving 28 percent of U.S. electric customers, including utilities in New York City, Michigan, Indianapolis, New England, Pennsylvania, the Carolinas and Florida, New Jersey and Georgia.

Those states presumably would be among potential markets for the wind-generated electricity moved from the Dakotas, Minnesota and Iowa, which have the potential to produce far more wind energy than would be consumed there.

Other states have their own plans

While Iowa has speckled its countryside with wind turbines, other states have similar aspirations.

Atlantic seaboard states advanced plans for offshore wind farms, which they say would eliminate the need to ship wind-generated electricity from Iowa.
Read the rest of this entry »

According to Forbes, parrotting a press release from Monitoring Analytics, the PJM 2009 year end State of the Market Report will be released by Monitoring Analytics on Thursday,  March 11, 2010, with a press briefing at 11:00 a.m. somewhere in Washington.  It will be available on the PJM site some time afterwards.  Monitoring Analytics is the firm that does the report for PJM.   Is Monitoring Analytics a PJM spinoff?

This is one of those reports that I’m really looking forward to…

Live from the BPU

February 11th, 2010

Susquehanna-Roseland… surprise, surprise, they just announced that they’re going to hold off until the end of the meeting, do everything else on a long agenda first… sigh…

bpu-2-11

Here we go  ROUGH NOTES

(with a few parenthetical comments)

BPU Agenda Meeting 2/11/10

Ken Sheehan: PSEG application.  Starts in PA, crossing to NJ at DWG, through 16 municipalities, following 230kV RoW.  PSEG building in conjunction with PPL in PA.  NJSA stt, taking it before the board, prove it is reasonably necessary (blah blah)

Three outstanding issues.

  • Request for Oral Arguments – staff recommends denial.  may be useful if parties have had opportunities to make arguments.  Wouldn’t appreciable add to process.
  • Request for Depositions – for 2 PSEG attorney re editing of PJM’s Herling’s letter.   Herling admitted they had made changes, but didn’t remember, and Motion followed.  Recommend denial of request.  Review has been minor, per Herling’s statement, board does not need additional info.
  • Request for Dismissal – Internvenors requested, also recommended it be denied.

Fiordaliso:  Are we to move on all of these now?

Ken Sheehan: Move after all the discussion.

Damase Hebert:  Background.  Proposed line is about 145 miles long, 45 miles of it is in NJ, crosses over Delaware Water Gap, Picatinny Arsenal.  2 switching stations, pursuant to a deal, agreed to move the Jefferson station to Hopatcong.  East Hanover, PSEG is willing to move to Roseland.  Entire project will cost between $900 million and $1.2 billion.  Interventions of Townships, Municipal Intervenors, Gerdau Ameristeel, Willow Lake Day Camp & Fredon Bd of Ed, Exelon,  Stop the Lines, Environmental Intervenors.  Participant status to National Park Service as requested.  Fiordaliso appointed to preside over hearings.   (Commission Fox gave someone a big grin at this point)  Public hearings and many written comments.  Fiordaliso conducted site visit, 3 locations.  Fiordaliso also presided over hearings, main topics covered included need, routing, engineering and construction, and electromagnetic fields.  400 exhibits and over 1,000 pages of transcripts (BFD!).  PSEG witnesses, 4 on need, 4 on routing, 3 on engineering and construction, and 2 on EMF.  Muni Intervenors sponsored 1 on need, 1 on EMF, and STL on ability of homes to obtain FHA mortgages.  Briefs, Muni Intervenors, Env Inervenors, Exelon, PSEG, Rate Counsel.  Reply Briefs too.  During December, delays in other PJM ordered PJM lines, PATH, and MAPP.  Board requested Sec.  send letter to PJM requesting more information,Herling response 1/21, reopened for a day of hearings.

Jerry May (?) to address need.

Jerry May: Relies on PJM analyses, that there will be violations of NERC by 2012.  (background on NERC).  PJM analyses through RTEP process also determined that S-R 500kV was the most appropriate remedy for the projected recommendations.  Intervenors have questioned the bases for assumptions and recommendations, available capacity and load.  PJM has estimated over 15 year planning horizon, 13 different bulk transmission lines are asspected to be overloaded in assumed single contingency events.  In addition, 10 are assumed to be overloaded for two lines on a single structure.  Further explanation of what violations mean. (he’s presuming it’s cumulative, but those subsequent iterations replaced the ones that no longer demonstrated need!)  Overloading of lines due to single contingency events is NERC Category B, while double contingency events are Category C.  A NERC category A evaluates with NO contingencies, and PJM found no violations of category A criteria.  PJM tests for load deliverability and generator deliverability.  Load deliverability addresses defined load levels and ability of xmsn to deliver adequat power.  Generator evaluates ability of generation to be delivered to PJM system at peak load conditions.  Normal Peak Day condition assumes tha based on historical data there’s a 50% chance of being warmer or cooler.  Emergency assumes only a 10% chance that the weather will be any hotter on that day.  NERC category B requires that the system be evaluated with one system out of service, purpose is to ensure that system continues to be reliabile with instantaneous outage.  For Cagoegory B, assumes emergency peak load for area being tested, and normal for rest of system.  For Category C, requires the system be stable and within system limits, under a variety of multiple system events, i.e., lost of one system element, adjustments, and loss of second element.  Double circuit tower line contingency that are the source of the cateogyr C violations projected by PJM in this proceeding.  For thistype, no system readjustments are permitted as both are removed from system at same time, using normal load, that these are rare and not necessarily tied to weather conditions.  Category B violations, PJM projected that violations would occur on two bulk power lines by 2012, and another 3 over next three years.  Over the entire forecast period, PJM estimates 13 lines would have violations of NERC Category B criteria.  12 fail load deliverability, and 1 fails generator deliverability.  Category C, ___ violations, over entire forecast violations, 10 lines would violagte category C criteia.  All of them ae due to failing the PJM generator deliverability test.  The NERC violations reflect PJM’s 2009 retool analysis.  Earlier studies dating back to 2007 resulted in different mix, but the conclusions from each was that NERC criteria would be violated by 2012 if NERC did not take steps.

In the past month, PATH and MAPP were either withdrawn or held in abeyance due to updated analyses that the project was not necessary in the time frame.  The Board directed that an additional hearing be held to determine what impact the delay in these lines would have for need for S-R. During the hearing, Herling reconfirmed PJM’s view that the project would continue to b enecessary to avoid violating NERC criteria as early as 2012.  …  that taking into account RPM auction, would not materially alter the conclusion. (WITHOUT ANY CITES OR SUBSTANTIATION!)

While PJM considered xmsn based alternatives, it found that none were as robust or would provide the long term solution.  PJM’s position with respect to alternatives, such as adding generation, DSM, heightened efficiency, was that it had no power to order added generation or DSM.  PJM’s contention was that transmission was the only measure that it had authority over to correct the violations.

Intervenors argued that the analyses are flawed, designed with a preordained conclusion, were challenging load forecasts, DSM, energy efficiency, and challenges more generally in the conservative nature of the PJM analyses.  As an alternative to outright rejection, some suggest PSEG should hold this petition in abeyance until next RTEP report is in.  Herling would not commit as to when the next RTEP would be completed, suggesting that the typical time frame is in the fall.  Intervenors point out that the latest Retool does not reflect RPM, where significant amounts of demand response capacity cleared, and which would be included as available capacity in the 2012 year, and would also be included in the next RTEP analysis.

Staff’s review of the record leads us to conclude that PJM’s process does not result in a preordained conclusion and produces results that are reasonable.  Intervenors complained that the most recent load forecast is too high, given the load drop.  There is a great deal of uncertainty about economic recovery, and staff does not believe that PJM’s load forecast is unreasonable.  PJM’s load forecast which reflected events since the last quarter of 2008, predicted drop of 1.4%, and actual drop in 2009 was 1.9% (not addressing that peak was in 2006 and it’s been falling).  While the forecast underestimated the severity of drop, it did reflect actual recent trend.  Economic growth projections used by PJM are geared to metropolitan areas located within PJM territory, and cannot be directly compared with national projections. (and PJM historic actuals and PJM trends?)  Staff agrees that the results of the May 2009 RPM auction should be included, but witness Herling explains why even incorporating these results would not alter conclusions.  Intervenors have noted that the May RPM auction resulted in significant demand response in those areas impacted, however witness Herling pointed out that demand response could not resolve Category C violations.  Demand response is not on call during normal periods and is not sufficient time frame to offset Category C violations.  Herling points out that while there was a significant demand response, there was a marked decrease in generation availability in relevant load zones, and net increase was relatively small. (note they never deal in impacts of energy efficiency, which reduces peak overall?)  In contrast, the increases in demand response capacity where PATH amd MAPP were planned were substantial, … those were violations that MAPP and PATH were designed to address.

Intervenors have argued that PJM has failed to consider additional demand response coming, pointing to the New Jersey Energy Master Plan, however the board’s main resonsibility is to assure safe and adequate supply of electricity.  Staff does not believe that PJM excluded the Energy Master Plan from models and consideration. (EH?)  Just as PJM models do not include demand response, it also does not include generation that may or may not occur  (yes it does, as he testified in the initial hearing, with different weights put on generation with an ISA and not).

Staff concludes that PSEG has met its burden that S-R is needed to avoid violations of NERC standards as early as 2010.  The number, nature and severity of the violations all bear this out (Say what?  Decreasing number, decreasing severity, and change in nature in blatant attempt to find some sort of violation).   Realistic variations in the various key inputs would, in staff’s opinion (training, experience, they’re NOT engineers!), still point to violations as early as 2012.  The fact that the violations grow throughout the forecast period points to the need for a robust response (they start at miniscule amounts above 100%, so small that FERC asked about optimization).

Next issue is routing.

Damase Hebert: PSEG presented expert testimony that Route B was most appropriate route.  Luis Berger retained to evaluate routes.  Berger reviewed 3 alternative routes, selected Route B, which follows existing line.  Impacts least area of forested land, impacts least amount of forested wetland, fewer streams crossed, no change in existing land use, crosses Appalachian Trail on existing 230kkV RoW, least distance of Highlands area crossed, all on existing cleared RoW, likely to have the least impact compared to the other alternatives routes because existing RoW would not have to be expand.  Staff recommends approval, because it runs along existing RoW, least impact compared to other route.  Minor adjustments may be appropriate.  Montville has requested move 3 specific towers, and staff reocmmends that Board direct PSEG to relocate or report why it’s not pssible.  In relation to routing issue, STL argued that existing residential homes within a specific distance no longer eligible for FHA.  Baord staff recommends further evaluation of this issue. Switching issues, Jefferson and E hanover, and alternatives were proposed.  Staff recommends moving substations.  Staff notes that use of existing RoW reduces impacts, if approved by board, towers will either be monopole or towers based on characteristics of route.  During course of proceeding, company changed from 4 to 3 conductors, impacts charactteristics of line, change is based on engineering requirements.  Likely to reduce EMF fields. (EH?).  Intervenors have not provided sufficient evidence to prove it’s not safe.  Comapny argues EMF is not dangerous, and EMF are below limits established by any state and regularly used appliances.  Staff has analyzed EMF testimony, and has comcluded that it will be below all established standards, and electrical fields will below NJ’s standards.  Staff recommends that the board require PSEG monitor EMF levels and report results to board, to demonstrate that this meets their state EMF levels.

Cost allocation methodology.  Current PJM tarrif regionalized it across PJM.  FERC has adopted paper hearing, which has been set in response to the remand from 7th circuit decision directing FERC to explain why current methodology is sound (NO IT DOESN”T, that is NOT what remand said and it is not what FERC is requesting in its Order to PJM).  It is unknown when the board will have complete certainty of cost allocation (short paper hearing process, it’s fast tracked).  Given long construction schedule, staff recommends the board not wait until cost allocation (Fox is smiling again at this point)

Staff urges that board issue an order that local zoning does not apply.  Board attach conditions:

– Board direct PSEG to work with Montville Bd of Ed to relocate towers to address their concerns.

– Company follow with report relocating 3 towers to relocate.

– Work in good faith to determine relocation of other alignments that are practicable

– Report within 90 days about other relocations, and if can’t, proceed as proposed.

– Continue to optimize locations of access roads, tower locations and structures, with other agencies to greatest extent possible.

– Evaluate issues explored about inability to obtain FHA mortgages.

– Monitor regarding EMF levels

– Work on continuing basis with fire and safety at Hopatcong and Roseland

– Avian protection plan with guidance from USFWS

– Board require the company to report to the Board the findings of PJM’s next RTEP analysis.  If that RTEP analysis finds that the project is no logner necessary or can be delayed significantly, staff recommends the Board retainspecific authoirty to reopen the proceeding.

– Hopatcong and Roseland switching stations, should routing require modifications, get approval from board.

– This route is located with areas governed by the National Park Service, Highlands Preservation Act and the Watershed Property Review Board.  Staff recommends that the board specifically state in its order that the order shall not be construed as certificate, license, permit to construct or disturb land in these jurisdictions until the company receives the relevant approval from these governing bodies and from any other non-municipal bodies.

Fiordaliso moved, ?? (male) seconded.

Fiordaliso – Having served as hearing officer, which has taken about a year to come to judgment, I feel confident that this board has fulfilled its duty to residents of state of NJ.  Staff committed time and resources, investigating every possible angle, trying to determine whether this is needed, to maintaini electrical service, for all their hard work, I would like to point out certain individuals (thanks staff).  Speed sometimes does not substitute for trying to get it right.  I have to indicate that this was the most difficult decision that I’ve had to make since I’ve been a member of this board, to weigh all the factors involved during the evidentiary hearings.  This was a fair and open process, everyone who wanted to participate could, I wanted them to walk out of the public hearing indicating that they could be heard.  I have heard from the public and witnesses, met with staff, examined every angle of this proposal when PATH and MAPP revelation occurred.  The only thing I could do was to take notice of that, and the supplemental hearing that we had htis month.  With that, it is my contention that it hinges on reliability, increasing infrastructure is a reasonable plan, everyone wants to avoid power outages plaguing our already fragile system.  This project is one part of a wider system, remain focused on renewable, but we have to ensure safe, reliable service for the state of NJ.  PSEG will work with other stakeholders so the process will be a fair and equitable one for all parties.

Butler:  I have nothing to add, I think staff’s analysis was thorough, I’m convinced this is needed.

Fox: Lot of questions and issues.  First, I want to let you know, I reluctantly will be voting for this.  I am hoping that we will not go through this again.  This is an issue of timing, what’s in front of us now (they could choose to wait a couple weeks for additional information that’s in the works).  NERC sets reliability standards, FERC picked NERC, this is based on need, balancing out reliability for the good citizens of this state.  Based on what we have in the record.  What is in the record says there is a need, in 2012.  Timing is everything, PJM projected then, it projects that now, violations in 2012, that’s a little over 2 years away.  It’ll take 18 months or so for this to be constructed.  Our first responsibility is reasonableness of service.  We are subject to a one year time constraint.  If we don’t decide this, we are told this will go to FERC and they will take over the case.  A lot has happened, an economic downturn has taken place, federal government is promoting appliance standards, GHG has not been passed but some day will have to be, NJ will establish more extensive programs to reduce electricity use, a large part revolves about how much it is reduced, we have clean energy, efficiency, renewable energy programs, most of that is not included by PJM.  The Energy Master Plan has reduction of energy use, that is not factored in.  FERC oversees PJM, this board does not.  PJM is largest wholesale power in the world, responsible to NERC and to FERC, they do not report to us (sure, give away your authority over transmission, good idea).  PJM’s RTEP, looks at transmission, generation, customer loads.  The higher the forecast.. PJM’s RTEP, category A, B, C violations were possible, and I think that NERC set these standards and the RTO’s are responsible for following.  Fine?  (from staff: Fine of up to $1 million a day).  Differences between MAPP and PATH, staff has asked for a briefing, two, and it comes down to category C violations, this is not responsive to demand response.  Herling testified that project would still be needed, not directly impacted by load forecast, so we still have this violation, the loss of double circuit line.  The issue I want to get to is risk.  How much risk are we willing to bear, how much are we going to take, prevent that from happening.  Herling had no knowledge of what that risk might be.  Modeling, when I was at EPA we did a lot of modeling, and I am not happy with how this is being handled.  TEAC is contemplateing using sensitivity analysis on load forecast, and the only information we have in the record is from PJM, taking into account different load forecast, using state’s projections, great idea, they don’t do that now.  How much are we going to pay for not having an outage.  Asked to look at actual peak loads in NJ, and it’s quite minimal.  From 06-09, the unrestricted load has exceeded peak for 44 hours.  What is the risk that we’re willing to pay for?  We are used to having outages, when weather occurs, and I’m sure we could probably pay away, that’s a risk analysis that I’m sure had been done.  Is the risk that we’re lessening here worth the cost of a billion dollar line balanced against cost and impacts.  We need to get PJM to look at risk of outage, balanced against category C.  NERC has been modified standards, but again, timing is the issue.  NERC requires RTOs to test events, each has their own internal test, as NERC modifies, they should consider consistent standards, tests, for all future analyses.  Federal Policy Act of s005, set up two NIETC, where here is a huge need, we’re smack in the middle of it, we’re paying more because we’re congested.  The recommendations staff did I thought were good.  I ask that my fellow commissioners to ask the RTO to develop some risk and cost benefit analysis if you don’t require it in their case, why would they), category C violations, having RTOs accountable.  What PJM did was require a billion dollar transmission project.  The existing record I don’t think clearly showed the impact of these violations, that our ratepayers are paying for (and you’ll approve it?  HELLO!?).  That needs to be done for any xmsn lines (like THIS one?).  When the RTO says it exceeds rating, we need to look at the magnitude.  Load forecasting needs to be modified in PJM, direct and indirect costs and benefits, i.e. EMF, does it fit here or not, I think that we really need to look at what raetpayers would pay.  Board has been working on effective alternatives to xmsn, national and regional level.  Our NJ Master Plan deals with that, and it is not in the RTEP model.  No one seems to have jurisdiction over generation. (well duh, you deregulated!).  New generation, existing generation, we don’t have control over instate generation, what goes out of service.  We need most cost effective way to look at generation, it’s probably in Washington, maybe us working with other states.   Due to timing of this issue, and what is in the record before us, there is not any real evidence looking at load forecasting, looking at forecasting, I’m obviously gong to have to vote for this (??? that conclusion makes NO sense) and obviously having reliability issues two years from that.

Nicholas Asselta: The reliability is what strikes me as the most important, infrastructure is what NJ is about today, and in the future, has to continue to move forward to make us economically viable.  We know what our situation is, we know what the situation of the US is in the world competitive market, it is the key for us to retain power.  I bleive this project is needed reliability wise, major imporovements, I support this project.

Elizabeth Randall:  We all went to staff over and over.  The need is critical, the category C violations are important, and it is unacceptable to do nothing, it is important to have reliability.

Fiordalis0: Forgot one of his extended family (moi) in the back.

Board: Unanimous vote.

(BARF – how disgusting can it get)

Getting railroaded?

February 2nd, 2010

093008str-17-erected

We all know what a pain in the patoot siting transmission is (particularly when it’s not needed).  And now for something completely different — an interesting and seemingly probable theory:

BNSF is looking at allowing electric transmission line companies us its rights-of-way “to send electricity from massive wind farms to major population centres” while giving BNSF access to “low-cost power for electric locomotives”. So rail might also be integral to Obama’s smart grid initiative by using railway cables and rights of way for electrical transmission. Norfolk Southern, has apparently joined BNSF in exploring electrification. Meanwhile, Union Pacific, the U.S.’s other mega freight rail company is apparently speaking to transmission line companies about providing its rights-of-way, that may include electrifying corridors.

ARE Y’ALL PAYIN’ ATTENTION??!!!?!?!?!

This is one of those pieces that I want to preserve to take out and reread in the not too distant future:

Buffett’s Semaphore Signal: Should Burlington Northern Shareholders Think Again Before Saying ‘Yes’ To Berkshire Hathaway?

Feb. 01, 2010

Author:  Daniel Sinclair

Reasons commentators ascribe to Buffett’s offer to acquire one of North America’s largestrail networks, Burlington Northern Santa Fe (BNSF) are now familiar. Growing global trade, continued reliance on (especially low sulphur) coal, a resurgent and growing US economy (without needing to pick product ‘winners’ and ‘losers’), a low risk way to gain exposure to any rising process for commodities, a hedge against inflation given rail’s pricing power, a competitive advantage in rail’s oligopoly and high barriers to entry, more productive rail with more efficient and technologically advanced operations and a rise double-decker railway carriages, a way to play higher oil prices and cap and trade or carbon tax laws given that rail is 3 to 4 times more fuel efficient than trucks.

Those reasons are all good, and they have been part of the core investment thesis for rail. But, it is submitted, there may be something extra that offers compelling upside to rail that has Buffett excited. Think about all the land that rail owns. BNSF, for example, operates one of the largest railroad networks in North America with about 32,000 route miles of track plus an additional 23,000 miles for other rail related infrastructure and property. Much of this land is of relatively little value beyond the use of rail. No one is going to build condos or hotels or new subdivisions along side railways.

Now think again. You think Boone Pickens has an ambitious plan for wind farms? Wait until you see what Buffett could do right across the US with his investment in BNSF. This land might become prime property for alternative energy generation including from wind and solar farms either side of rail tracks. With much of rail land in the middle of nowhere, there are few worries about the ‘not-in-my-back-yard’ crowd and more difficult regulatory approvals. Small wind mills and solar panels might be placed on the trains themselves to generate energy.

Read the rest of this entry »