From the public meeting materials, here’s what they’re looking at, above.  These are significant additions to the transmission grid in Minnesota and Wisconsin.

MISO’s Economic Planning Users Group is planning a “Regional Transmission Overlay Study” and they’re having another meeting tomorrow, May 25, 2017 down in Metatairie, Louisiana.

Here’s the call in info:

WebEx Information
Event Number: 966 575 350
WebEx Password: Ts824634

Participant Dial-In Number: 1-800-689-9374
Participant Code: 823713

Meeting Materials from the MISO site:

Here’s the problem — they close the meeting, and people like me aren’t allowed to attend.  First I was told, back in January when I tried to register:

Thank you for registering for the Economic Planning Users Group (EPUG) on Jan 31.  The afternoon portion of this meeting will be held in CLOSED session and reserved from MISO Members or Market Participants only.  Please feel free to attend the morning session from 11:00 am to 12:45 pm ET / 10:00 am to 11:45 CT.

I filled out their “CEII – Non-Disclosure Agreement” form and fired it off.  But noooooo…

So next I went to the PUC’s Quarterly MISO update, where I was assured that we could make arrangements so that I could attend.  I resent the “CEII – Non-Disclosure Agreement” and went back and forth and it came to this (click for larger version).  Note this “explanation” of options to be able to attend:

The reason that you were not permitted to attend the closed session is because the meeting involved discussion of Critical Energy Infrastructure Information (CEII) and CEII access requests by Non-Member Individuals requires FERC clearance.  Another access option is to be included on Appendix A of a MISO member or Market Participant.

So that says there are two ways to gain access, 1) get “FERC clearance” or 2) “Another access option is to be included on Appendix A of a MISO member or Market Participant.”  One or the other. Emphasis added.  Here’s the email (click for larger version) laying out those two options:

Oh, I says to myself, off to FERC.  I sent in the requisite paperwork to FERC, and got “FERC clearance” and they shipped me the CEII information, including but not limited to the map.  I let MISO know I’d obtained “FERC clearance,” and here’s the response (click for larger version):

ARRRRGH, they have my CEII NDA on file, have had it since January 23, 2017.  I resent it to the writer of these emails on March 4, 2017, and I sent it again today, and objected to yet another change in their “rules” (click for larger version):

So the plot thickens — from MISO (click or larger version):

And from moi (click for larger version):

James McIntyre was shot outside an open house for a dam project, “Site C” for the dam.  You know, those open houses they hold to tell the public what they’re going to do before they do it… There was an investigation of the shooting by Canada’s “Independent Investigations Office,” and I’d had an alert and checked now and then, particularly a year after the shooting, but didn’t find the articles on the IIO’s November release of information until yesterday!  Here’s the report from the IIO:

07-16-2015-Dawson-Creek-Firearm-Death-2015-000104

Here are some press write ups:

Police ‘begged’ Site C activist to put down knife before shooting him, witness says

IIO clears RCMP in shooting of James McIntyre

RCMP officers cleared in shooting death of Site C protester in Dawson Creek

Look at the way the press framed this article:

RCMP officer cleared in shooting death of B.C. activist that sparked Anonymous revenge campaign

This shooting of McIntyre hit home for me because of my routine of going to the open houses and hanging out at the door, and I know so well how angry people get when there’s infrastructure proposed in their community, on their land.  They published my LTE about this in the Alaska Highway News:

UTILITY INFRASTRUCTURE LEAVES DEEP IMPACTS

Your coverage of the RCMP shooting of James McIntyre has been thorough in this general dearth of information.

I’ve spent the last 20 years advocating against utility infrastructure in the U.S., and the killing of McIntyre by RCMP is horrifying.  

A big part of my schtick is to stand at the door (not inside where I’d be “interfering”) and enthusiastically greet everyone, hand them a flyer about how to participate, and direct them to the meeting.  Had I been at that open house, I’d be the one they found at the door.  Had they told me to leave, I’d have argued and resisted, as always, ramping up if they pushed.

In my experience, utilities have now and then requested police presence, and when I see it, I let the organizers know it’s offensive and off putting, chilling public participation.  People have a right to speak out against a project, and they have a right to be angry!  I talk to the officers too, find out if I can who wanted them there, and let them know it’s inhibiting and threatening to the public.  I figure they just add me to their list of people to watch.  But this atmosphere of blind fear is not acceptable.  Don’t Canadians have a right to free speech?  Civil disobedience is an appropriate response.  Civil disobedience is NOT a death sentence with law enforcement as judge, jury and executioner.

People are being steam-rolled by utility infrastructure projects such as dams, transmission lines, and pipelines, and no one wants to hear about it.  They want opposition to just go away.  People are losing their land, communities are deeply affected, and those affected are not compensated sufficiently to make it acceptable — and money is not the answer to everything!  

Is the Site C project worth the impacts?  Is generating electricity and profiting from it sufficient reason to inflict these impacts, including this death?  Maybe BC Hydro should think again.

—Carol A. Overland, Utility Regulatory Attorney, Minnesota

Here are my older posts about the shooting, including a video of the shooting by someone in the hotel who was looking out the window:

RCMP shoots hydro dam protester? Nope, misidentified!

James McIntyre ID’d as man shot by RCMP

It’s been a year since McIntyre was shot in BC

RICL?  That’s the “Rock Island Clean Line.”  Yes, that’s an oxymoronic moniker.  Today, this project is on the chopping block, the oral arguments in their challenge of Illinois’ rejection of this project is at issue.  Last gasp…

Here’s the AUDIO LINK to today’s arguments.

How could I forget?  Badger Coulee transmission is marching through Wisconsin, and here it is, framing the entrance to Mirror Lake State Park.  UGLY!

And it goes from bad to worse:

See the trail by the I-90 and I-94 signs in the upper left, it’s a dashed line?  That trail is right under the transission line.  The park ranger said ATC/Xcel was good to work with, that they paid them to move the trail, though it still goes right under the line in one place.

 

 

The Minnesota Public Utilities Commission rulemaking for Minn. R. Ch. 7849, Certificate of Need, and 7850, Routing and Siting, is slowly moving forward. Here are the final drafts up for review before they go to the Commission for a rubber stamp and release for general comment:

20173-129606-02_Draft 7849

20173-129606-03_Draft 7850

Final initial comments on drafts were due on Monday and here they are, in alphabetical order:

20175-131641-01_Commerce DER

20175-131640-01_Commerce EERA

20175-131687-01_Goodhue Wind Truth – Marie McNamara

20175-131650-01-1_Great River Energy

20175-131683_ITC Comments and Attachments

20175-131698-01_Just Change

20175-131686-01_NoCapX – U-CAN – NRG & GWT

20175-131675-01_Wisconsin Power & Light

20175-131688-01_Xcel Energy

Reply comments are due by 4:30 p.m. on May 31, 2017.  eFiling is preferred!  If you need to register to eFile, GO HERE!  It’s easy, quick, and makes filing a breeze.  Get to work — there’s a lot here to comment on!