CANCELLED – TOMORROW’S MEETING HAS BEEN CANCELLED. Received phone call from PSC Counsel, and it’s on their event calendar.


TOMORROW! Wisconsin Public Service Commission (PSC) is set to decide whether the 300 MW Badger Hollow solar project should be issued a CPCN. This is the biggest solar project in the Midwest, and it’s proposed for prime ag land, in “Exclusive Agricultural” zoning, and the PSC has NO solar siting rules. WHAT? We tried, filed a Petition for Rulemaking, but they tossed it out. Who needs rules for siting…

Something I don’t understand about Wisconsin’s Public Service Commission — they don’t give adequate notice for their meetings. I checked yesterday, nada, but today, the notice for TOMORROW’S meeting is now posted.

We’re items 6-8. The meeting starts at 10:30 a.m. (oh my, another early start this week!), and I’ve seen them ram through docket after docket at breakneck speed, sooooo, heading east at “too early o’clock.”

To check the dockets for these projects, go to HERE: PSC HOME PAGE SEARCH and search for:

  • Project-Site CPCN: 9697-CE-100
  • Project-Transmission: CPCN 9697-CE-101
  • Acquisition Docket: 5-BS-228


Here we go again…  On January 24th, Wisconsin’s Public Service Commission denied the Petition for Rulemaking filed by Jewell Jinkins Intervenors, where we’re trying to get them off the dime and promulgate some solar siting rules.

Petition for Rulemaking_JJI_Solar_FINAL

Here’s their written order, just out today, with some bizarre statements:

PSC Order_2-6-2019- Denial of Rulemaking Petition

Bizarre statements?  Yup, here’s one, the grand finale:


As Bob Cupit would say that I say, “GIVE ME A BREAK….”

MGE & WPSC shot down!

January 9th, 2019

This has been one of the longest weeks, if I were a driver, I’d be out of hours after tossing my 2nd log book in the bunk!  But hey, that’s why they call it work.  This Order helped make it all worthwhile.

Order –  Denying MGE-WPSC Motion to Protect

MGE and WPSC have been working so hard to keep Jewell Jinkins Intervenors out of this docket, and we end up spending all our time on challenging the onslaught.  Today’s Order follows the PSC denial of their Motion to have us tossed out:

WPSC_MGE Motion for Interlocutory Review_354992

Which followed their previous Objection to our Intervention, which was also tossed out:

Applicant Response to Motion to Intervene

Order_Intervention

At long last, this… ONCE MORE WITH FEELING:

Order –  Denying MGE-WPSC Motion to Protect

It’s hard to pick my favorite part, this is for sure in the Top 10 of all time.  How’s this for a snippet?

Onward.  Today after this Order, I received their Confidentiality Agreements, signed them and shipped to the utilities, and then the Discovery started coming in.  Lots and lots and lots and lots and lots.  Rebuttal is due tomorrow.  Right…

Photo of DOE project in Alamosa, under 30 MW

There’s a 300MW solar project proposed for southern Wisconsin, in Iowa County.  Thing is, as with Minnesota and large wind (PUC denies Reconsideration re: Wind Rulemaking), there are no siting rules for solar in Wisconsin!  Really, no rules!  Typically thus far, solar projects are 2-10 MW.  This one proposed is 300MW!  Central station power to put it mildly.

Not only are there no siting rules, but there is no Environmental Impact Statement required for a project covering 3,500 acres!

WHAT?!?!

So on behalf of Jewell Jinkins Intervenors, I’ve just filed this Petition for Rulemaking to get them going on solar rules.

Petition for Rulemaking_JJI_Solar_FINAL_Signed

We shall see what, if anything, they do.

Lots of filing in Wisconsin

November 20th, 2018

Apparently Invenergy doesn’t like the idea that we’re intervening in their Wisconsin dockets.  I guess after Freeborn Wind, it’s not hard to understand why.

Intervention in Badger Hollow HUGE 300 MW solar project docket — approved by the Administrative Law Judge (Docket 9697-CE-100):

Jinkins Jewell Wendhausen_Intervention

Order_Interventions_11-1-2018

And then the related dockets, the transmission line and the acquisition docket, appropriately known as the BS docket, our intervention, their objection, and our response.  The transmission docket (Docket 9697-CE-101):

Jewell Jinkins_101_Intervention_FINAL

9697-CE-101 Badger Hollow – Response to Request for Intervention (Objection!)

Jewell Jinkins Intervenors_101_Reply to Objection

And the acquisition BS docket (Docket 5-BS-228):

Jewell Jinkins_228_Intervention_CORRECTED

Applicant Response to Motion to Intervene (Objection)

Jewell Jinkins Intervenors_228_Reply to Response

Oh, and the Cardinal Hickory Creek 345 kV Transmission Line!  Docket 5-CE-146.

Jewell Jinkins Intervenors_Cardinal-Hickory Creek_Intervention

To look up any of these dockets, go to the Wisconsin Public Service Commission’s Search site, and  plug in the numbers.

Meanwhile, we’re waiting on the Minnesota Commission meeting on Reconsideration for our Rulemaking Petition, and waiting on two orders, project and transmission, for Freeborn Wind.

And around all these filings, I’ve been to band practice, made wild rice and garbanzo salad, and I hear a Ferndale Market turkey calling…

What a long week it’s been!  WHAT?  Tuesday?!?!  No, really?!?!