Another coal gasification bites the dust — yes, it took a coon’s age to get this posted, what can I say, the CapX hearings are taking up a lot of time… This was the best news in ages, continuing the theme that IGCC is a bad idea, too risky, too costly. This plant was one that seemed to have a lot of backing, which to me means that IGCC is done. When I’d posted about it, it garnered some wild NRG employee comments on this blog, ones that I hope that those employees’ bosses are aware of! I know NRG is watching, but I think some of their employees need to have their typing fingers taped together and/or not operate a computer while soused!

Here are a few articles with some choice comments:

From the Buffalo News:

Power Authority stops $1.6 billion plans for advanced coal plant at Tonawanda’s Huntley Station

Power Authority officials estimate that it would take an additional $175 million to $200 million per year in subsidies – on top of the significant aid already promised for the project – to bring the price of the electricity produced at the advanced coal plant down to the point where it could compete with other conventional sources of generation.

From newsday.com:

NYPA halts plans for clean-coal plant in Tonawanda

After pursuing various state grants and tax incentives, NYPA determined it is not possible to fully close the gap between what NYPA would have to pay for electricity and competitive market rates.

And from the Post Journal:

NYPA withdraws support for North Tonawanda clean coal project

”The economic, technological and regulatory obstacles are too great to warrant any further efforts at this time,” said Christine Pritchard, a NYPA spokeswoman.

… and…

NYPA officials were also uneasy about the technology. According to the company, there are only two IGCC plants operating nationwide, and 11 IGCC plants were either delayed or cancelled in 2007. In addition, the largest sequestration operation in the world is burying only 1 million tons of carbon dioxide underground annually, a third of what the NRG plant would be required to sequester – and carbon capture and storage technology has never been demonstrated off a clean coal power plant.

… and…

”It is also clear that an explicit and rigorous regulatory process with public support is a prerequisite for sequestration on a large scale. And while some amount of risk is necessary to prove new technology, the financial and environmental risk associated with this large-scale commercial power plant is simply too great,” the report concludes.

… and…

”Simply, at this time, the price gap is too large to overcome” said Pritchard of NYPA.

Tell us something we didn’t already know!!!